Revamping Of Waste Water Treatment Plant in the Refinery

Project granted on: April 2014 – Ongoing

Project Summary: Designing, refurbishment (Site clearing of the old equipment; Early site redevelopment works; Demolition of old discharged machinery and equipment’s foundations; Concrete foundations works for new equipment; New equipment installation; Posing/connecting new pipes and hoses), Start up and Supervision of Waste Water Treatment Plant KAR 1 belonging to Kar Group. (40 – 50 m3/h oily waste water)

 